Airmaster Air Conditioning, company logo
Follow Airmaster on facebook Keep up to date with Airmaster on LinkedIn Keep up to date with Airmaster on Twitter
Tel: 0114 288 9911 Click to view Navigation

Case Studies

B&Q Distribution Centre, Worksop

B&Q Distribution Centre, Worksop main image

As a Daikin D1+ dealer & installer, Airmaster Air Conditioning Ltd along with several other local D1+ rated companies were invited to tender for the large Air Conditioning replacement project at the B&Q Distribution Centre in Worksop.

We were asked to present 2 tender applications, the first to carry out a full like-for-like AC replacement of the existing 15 year old Sanyo systems, the second was to put forward our own design & build application.

The Airmaster Contracts team presented a perfect tender application which included a full Hevacomp thermal imaging building report, giving us the precise up to date technology to supply the correct AC equipment in the right areas, this was carried out by our in house Design team at Airmaster Air Conditioning Ltd.

The project included; the full removal of the existing AC systems, with full replacement of 6 large Daikin Europe VRF systems, 2 Comms room double split systems, the project also included the Daikin ‘reclaim with confidence’ and ‘commission with confidence’ package. This was finished with a full mains electrical upgrade to all internal and external AC systems.

This was carried out on a very tight 8 week timeframe, along with all buildings still in full use and strict Covid restrictions earlier this year, the Airmaster Air Conditioning Ltd team pulled out all the stops to complete a fantastic project on time.

The B&Q Worksop Engineering & Facilities Manager Dave Horton and his team were brilliant to work with and had nothing but praise for the Airmaster installation Engineers.

To download a PDF of the case study please click here. 

Paul Wilkins, Corporate Clients Division Manager at Daikin

“Well done to everyone involved at Airmaster Air Conditioning Ltd. Your tender submission was spot on, fulfilling the brief perfectly and then going beyond it too. The project ran like clockwork thanks to your professionalism. The client understood the long-term importance of marrying a high-quality installation with high quality equipment. A great project.”

B&Q Distribution Centre, Worksop small left thumb
B&Q Distribution Centre, Worksop small right thumb

Pharmaceutical / Health

Pharmaceutical / Health main image

Airmaster have completed the full design and build mechanical install of specialist laboratory systems for a pharmaceuticals company in the health sector.

The install compromised of:

Flexible LEV extraction arms in the laboratories.

Dedicated plastic fume extraction systems to the fume cupboards up to roof level duty/assist centrifugal fans and purge stack.

All this controlled via an Easylab VAV damper system to keep the pressures in balance when the environment changes.

Magnehelic Gauges were installed at each entrance to show the pressure reading of the room, each with its own specific requirement.

The general ventilation was supplied via packaged Air Handling Units with LTHW frost coil via an Air Source Heat Pump and DX heating/cooling coils.

Fan units were installed throughout the floors with VRV Condensers providing comfortable temperature control to the office and laboratories via secondary high induction supply grilles.

All roof systems required walkways and handrails manufacturing to provide safe access.

Other systems installed include a Comms Room AC split system, a -20 degree freezer room build and refrigeration install for material storage.

Stainless steel ductwork and plastic fan to specialist ICPMS lab equipment to deal with chemical fume extraction. Buffer vessel and pump set configuration within the plantroom.

And finally, a full public health install of sanitary ware and laboratory sinks and basins and safety shower, POU water heaters, high efficiency twin water softener and GRP storage tank with twin headed booster pump.

All systems controlled and managed via a fully integrated BMS system with head end PC and graphics.

Download the full PDF case study here.

 

A great team effort by all, from the conception of Airmaster's team of designers which made all that came after run and work smoothly. The install with our own contracts engineers and site supervision completed the whole project within a 13 week programme!

The team also completed a 2 week commissioning phase at the end to balance the systems in a -10pa lab environment.

Pharmaceutical / Health small left thumb
Pharmaceutical / Health small right thumb

Business Park Offices

Business Park Offices main image

The photos below are from whilst we were completing a mechanical fit in Watford. The landlord owned various buildings on the business park and there was a relatively new Daikin chiller on the roof that was surplus to requirements due to the whole building converting to VRF/V.

There was however another chiller at the end of its life on another building so whilst in contract and to make space for our new condenser banks we successfully disconnected both chillers, controls power and water, craned the old one off to be disposed, then the new one off one building, re set up the crane location to lift it onto the other building in the same day.

Then the week that followed, re piped, dosed, insulation and cladding, power, BMS, water balancing and commissioning. Needless to say good planning, preparation and communication meant this all went smoothly and we envisage for every project.

Business Park Offices small left thumb
Business Park Offices small right thumb

Major chiller refurbishment for British multinational, York

Major chiller refurbishment for British multinational, York main image

Airmaster were presented with a unique challenge in refrigeration when tasked with the refurbishment of two chiller’s in one of York’s most stunning buildings. The chiller systems which run throughout the 6-storey building were circa 27 years old and required a number of significant repairs for future system resilience and life span longevity. With such old systems in place, parts were now obsolete and more importantly inefficient. The core focus of this project was to modernise the existing chiller systems making them more durable and efficient to compete with modern day chiller technology, all while offering a great value engineering solution beneficial to the end users budgets.

The heart of this chiller refurbishment lies in the basement where the compressors, evaporators and control panels are situated. The basement plant room is a congested area filled with mechanical equipment and associated electrical equipment. All twelve compressors had to be manoeuvred carefully out of the space safely and taken away for full refurbishment. All the refrigerant pipework, NRV’s, mufflers, vibration eliminators, ball valves, pipe insulation and pipe clamps were replaced for new in the plant room and roof top condenser area.

New Carel ExV electronic expansion valves replaced the existing dated originals. These new valves specifically focus on energy efficiency, in addition they produce high levels of precise refrigerant control passing through the evaporator.

New Airedale control panels also replaced the existing panels. The new control panels utilise a microprocessor controller taking full advantage of the latest state of the art technology.

The control system comprises of three main parts, the controller with built-in user interface, electronic expansion valve drivers and head pressure control. The display keypad is used for viewing the unit operating status and making adjustments to control parameters by allowing the operator access to a series of display pages. Visual alarm and the facility to adjust and display control settings are available at the display keypad for local operator information and control.

The chillers initially used refrigerant R22 but this was eventually phased out, MO29 (R422D) was chosen as the replacement around 10 years ago but ultimately this wasn’t a success. After diligent research, a reasonably new refrigerant to the UK market was chosen, RS70 (R453A). The focus was energy efficiency and compatibility with the systems as a whole. RS70 has a cooling capacity within 3% of R22 and has the highest efficiency rating plus the lowest GWP (1765) of all the R22 replacements currently on the market. In total, both chillers used 2,400kg of RS70.

Both chillers housed four Searle GEA condensers in total, consisting of 48 Ziehl Abegg fan motor assemblies. Twelve of the original motors were found to be faulty and were replaced with the new type Ziehl Abegg FN091. Once again, energy efficiency took president, the FN091 use EC fans and motors with maximum efficiency. The motors are controlled via pressure transmitters to the exact speed required, which in turn provide pin point operating pressures of the new refrigerant.

This was a delicate project handled with great care by the engineering team at Airmaster, who continue to grow as rising stars in the refrigeration sector. The refurbishment saved hundreds of thousands of pounds for the builder owners and provides the onsite PPM team a much more proactive way of controlling the buildings comfort conditions without the reactive issues presented by the chillers previous condition.

To download a PDF of the case study please click here.

Major chiller refurbishment for British multinational, York small left thumb
Major chiller refurbishment for British multinational, York small right thumb

Accreditations